What to send for a metal roof takeoff

A sketch, a panel list and a trim list answer three different questions. Here’s how to put them together for a material quote.

Start with one labeled sketch

Give each roof face a letter. Use the same letters on your sketch, photos and panel list. Mark which way the panels run. That small step lets the supply desk tell whether “13 feet” means a panel length, a ridge or an eave.

Give each panel length its own line

For a simple example, write “Face A · 21 panels · 13 ft 2 in each.” Keep feet and inches separate: 13.2 feet is not 13 feet 2 inches. If two faces have different lengths, keep them on separate rows even if the color matches.

  • Quantity and length for each panel group
  • Panel profile and coverage width, including any areas that need a different profile
  • Color and gauge if known; mark undecided items rather than guessing
  • Whether each length is a field measurement or an approved finished cut length

Keep trim separate from panels

Label each eave, ridge, rake, valley and wall intersection on the sketch. Supply the measured runs, not just the number of pieces you expect to buy. If a bend needs to match an existing detail, attach a dimensioned sketch showing the finish side.

If all you have is a photo

Send the address or a map pin and whatever ground-level photos you already have. That’s enough to start a conversation, but a photo alone won’t establish finished cut lengths. Keep unverified measurements marked as estimates and confirm dimensions before fabrication.