Name the edge before measuring it
An eave is the lower edge where water leaves the roof. A rake is the sloping edge at a gable. A ridge joins two roof faces at the top; a valley is the inside intersection between faces. Label these on the sketch before totaling anything.
Record runs, not just total footage
Two separate 12-foot eaves and a single 24-foot eave have the same total footage but may need different piece layouts. List each run with its own start and end. Let the supply desk confirm stock lengths, laps and how many pieces make sense.
Show the wall detail
Where the roof meets a wall, a straight-on photo and a labeled side sketch can answer questions a plan view can’t. For custom bends, give leg dimensions, bends and the side that shows the finish. Identify the mating panel profile so the desk can confirm compatibility.
Before requesting a quote
Send the panel finish and color with the trim list. A homeowner comparing samples and a contractor replacing one piece both benefit from checking the actual finish rather than relying on a screen color.
- Roof-face ID and edge type
- Individual measured runs with units
- Sketch and photos for nonstandard bends
- Color, finish side and panel profile